ISA ENERGIA BRASIL is constantly evaluating opportunities in the market for its growth and has made progress in this area. The Company's strategy consists of expanding its presence in the national territory through auctions and/or acquisitions that generate synergies with existing operations, while respecting the minimum required return.

Since 2016, the Company has secured nineteen lots in transmission auctions held by ANEEL, totaling ANEEL investments (weighted by ISA ENERGIA BRASIL's participation) of R$ 15.8 billion, with an increase in RAP (2025/2026 cycle) of approximately R$ 2.1 billion following the commissioning of these assets.

Summary table, download below.

For complete information, click here

Company Contract Project Expiration Operational
Status
Next Tariff
Review
RAP  ISA ENERGIA BRASIL Cycle 2025/2026 (BRLmillion) Adjustment
Index
ISA ENERGIA BRASIL's
Share (%)
ISA ENERGIA BRASIL 059/2001
008/2022
012/2016
006/2023
012/2023
Concessão Paulista
Piraquê
PBTE
Serra Dourada
Itatiaia
SP
MG / ES
SP
BA/MG
RJ/MG
31-Dec-42
30-Sep-52
21-Nov-46
29-Sep-53
29-Sep-53
Operational
Under Construction
Operational
Under Construction
Under Construction
2028
2028
2027
2029
2029
3.546,4
343,1
234,8
321,8
248,2
100%
IE Aguapeí 046/2017 Aguapeí SP 11-Aug-47 Operational 2028 83,2 100%
IE Riacho Grande 005/2021 Riacho Grande SP 31-Mar-51 Under Construction 2025 93,1 100%
IEMG 007/2020
004/2007
Triângulo Mineiro
IEMG
MG
MG

20-Mar-50
23-Apr-37

Operational
Operational
2025
n.a.
46,1
15,4
100%
IE Itaúnas 018/2017 Itaúnas ES 10-Feb-47 Operational 2027 72,1 100%
IE Itaquerê 027/2017 Itaquerê SP 11-Aug-47 Operational 2028 70,8 100%
IENNE 001/2008 IENNE PI / TO / MA 16-Mar-38 Operational 2028 71,4 100%
IE Serra do Japi 026/2009 Serra do Japi SP 18-Nov-39 Operational 2025 62,4 100%
IE Jaguar 9 015/2008 Getulina, Mirassol e Aráras SP 15-Oct-38 Operational n.a. 77,3 100%
IE Biguaçu 012/2018 Biguaçu SC 20-Sep-48 Operational 2029 56,3 100%
IE Jaguar 6 143/2001
042/2017
Botucatu-Xavantes
Bauru
SP
SP
11-Aug-47
20-Mar-50
Operational
Operational
n.a.
2028
20,6
16,2
100%
IE Jaguar 8 011/2022
012/2008
Jacarandá
Piratininga
SP
SP
21-Sep-48
9-Dec-41
Under Construction
Operational
2028
n.a.
16,1
16,0
100%
IE Tibagi 026/2017
006/2020
014/2023
Tibagi
Três lagoas
Água Vermelha 
SP
MS / SP
MG
15-Oct-38
15-Oct-38
21-Sep-48
Operational
Operational
Operational
2028
2025
2029
23,7
7,5
8,5
100%
IESUL 016/2008
013/2008
Forquilinha
Scharlau
SC
RS
20-Dec-31
11-Aug-47
Operational
Operational
n.a. 20,4
8,8
100%
IE Itapura 021/2018
021/2011
Lorena
Itapeti
SP
SP
30-Sep-52
15-Oct-38
Operational
Operational
2029
2027
18,3
9,2
100%
IE Pinheiros 018/2008 Atibaia II SP 15-Oct-38 Operational n.a. 8,6 100%
IE Madeira 013/2009
015/2009
Lote D
Lote F
RO / SP / MT / MS / GO 25-Feb-39
25-Feb-39
Operational
Operational
n.a. 208,3
179,7
ISA ENERGIA BRASIL 51% / Furnas 24,5% / Chesf 24,5%
IE Ivaí 022/2017 Ivaí PR 11-Aug-47 Operational 2028 199,4 50% / TAESA 50%
IE Aimorés 004/2017 Aimorés MG 10-Feb-47 Operational 2027 54,4 50% / TAESA 50%
IE Garanhuns 022/2011 Garanhuns PE / AL / PB 9-Dec-41 Operational 2027 80,5 51% / Chesf 49%
IE Paraguaçu 003/2017 Paraguaçu BA / MG 10-Feb-47 Operational 2027 81,2 50% / TAESA 50%
#22 Total (34)         6.373  
                 
Operational             5.350,5  
Under Construction             1.022,3  
Total             6.372,8  
The Annual Permitted Revenue “RAP” of all contracts is annually adjusted by the IPCA, with the exception of contract: 143/2001 which is adjusted by the IGPM.
Substation Map
Company / Project June 30, 2025
Transmission Lines (km) Circuito
(km)
Substations Transformation Capacity
(MVA)
Operational1 20.317 28.224 129 78.336
ISA ENERGIA BRASIL 14.633 19.504 109 50.184
IENNE 711 711 - -
IEMG 173 173 - -
IE Pinheiros - - 1 400
IE Serra do Japi - - 2 2.000
IESUL 179 202 2 900
IE Itapura - - 1 2.000
IE Madeira 2.385 4.770 - 7.464
IE Garanhuns 633 633 2 2.100
IE Itaquerê - - - 900
IE Tibagi 54 71 - 900
IE Aguapeí - - 2 1.400
IE Biguaçu 38 54 1 300
IE Jaguar 6 137 137 - 250
IE Jaguar 8 1 1 1 1.200
IE Jaguar 9 - - 3 2.400
IE Aimorés 208 208 - -
IE Paraguaçu 338 338 - -
IE Ivaí 593 1.186 1 2.988
IE Itaúnas 77 77 1 1.350
Triângulo Mineiro 158 158 3 1.600
Minuano 77 77 1 2.691
Água Vermelha - - - 400
Under Construction 2.604 3.299 7 3.850
IE Riacho Grande 30 60 1 800
Piraquê 936 1.078 2 2.250
Jacarandá - - - 600
Serra Dourada 1.116 1.116 3 200
Itatiaia 522 1.044 1 -
Total 23.162 31.763 139 85.727
1 Project information 100%

Click here to download the spreadsheet.

Updated on August 14, 2025.